Order #100122

Billing SentNormal priority

Northline Foods · Bundle Pack 2x run · PRJ-2042 · due Jul 14, 2026

100%

500 / 500 units · 0 remaining

Open labor trackerBilling sent Jul 15, 2026

Production progress

Completed

500

Required

500

Remaining

0

Complete

100%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Assembly5005000Per Unit @ $0.754046On Track
Picking / Prep5005000Per Unit @ $0.15150159.7On Track

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate13.3 hrs
Manager estimate14.7 hrs
Actual labor13.99 hrs
Projected final14 hrs
Variance-0.7 hrs

Productivity

Expected units/hr95
Current units/hr71.5
Difference-24.74%
StatusWatch
Historical rate46 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work0 units
Current rate71.5 units/hr
Projected remaining labor0 hrs
Actual labor used13.99 hrs
Projected final labor14 hrs