Order #100125
Billing SentNormal prioritySolace Beverages · Travel Kit run · PRJ-2045 · due Jul 23, 2026
100%
900 / 900 units · 0 remaining
Open labor trackerBilling sent Jul 24, 2026
Production progress
Completed
900
Required
900
Remaining
0
Complete
100%
Services
| Service | Required | Completed | Remaining | Billing | Expected /hr | Actual /hr | Status |
|---|---|---|---|---|---|---|---|
| Kitting | 900 | 900 | 0 | Per Unit @ $0.50 | 62 | 64.3 | On Track |
| Picking / Prep | 900 | 900 | 0 | Per Unit @ $0.15 | 150 | 138.7 | On Track |
Active employees
No employees clocked in on this project.
Labor summary
Historical estimate19.5 hrs
Manager estimate21.5 hrs
Actual labor20.49 hrs
Projected final20.5 hrs
Variance-1 hrs
Productivity
Expected units/hr106
Current units/hr87.8
Difference-17.17%
StatusWatch
Historical rate64.3 units/hr
Based onLast 1 similar projects
Projected completion
Remaining work0 units
Current rate87.8 units/hr
Projected remaining labor0 hrs
Actual labor used20.49 hrs
Projected final labor20.5 hrs