CCProduction & Labor
MA
← All projects

Order #100125

Billing SentNormal priority

Solace Beverages · Travel Kit run · PRJ-2045 · due Jul 23, 2026

100%

900 / 900 units · 0 remaining

Open labor trackerBilling sent Jul 24, 2026

Production progress

Completed

900

Required

900

Remaining

0

Complete

100%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Kitting9009000Per Unit @ $0.506264.3On Track
Picking / Prep9009000Per Unit @ $0.15150138.7On Track

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate19.5 hrs
Manager estimate21.5 hrs
Actual labor20.49 hrs
Projected final20.5 hrs
Variance-1 hrs

Productivity

Expected units/hr106
Current units/hr87.8
Difference-17.17%
StatusWatch
Historical rate64.3 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work0 units
Current rate87.8 units/hr
Projected remaining labor0 hrs
Actual labor used20.49 hrs
Projected final labor20.5 hrs