Order #100129
Billing SentNormal priorityKirra Outdoors · Gift With Purchase run · PRJ-2049 · due Aug 4, 2026
100%
500 / 500 units · 0 remaining
Open labor trackerBilling sent Aug 5, 2026
Production progress
Completed
500
Required
500
Remaining
0
Complete
100%
Services
| Service | Required | Completed | Remaining | Billing | Expected /hr | Actual /hr | Status |
|---|---|---|---|---|---|---|---|
| Kitting | 500 | 500 | 0 | Per Unit @ $0.50 | 62 | 69.7 | On Track |
| Inspection | 500 | 500 | 0 | Per Unit @ $0.28 | 100 | 89.3 | Watch |
Active employees
No employees clocked in on this project.
Labor summary
Historical estimate12.1 hrs
Manager estimate13.4 hrs
Actual labor12.77 hrs
Projected final12.8 hrs
Variance-0.6 hrs
Productivity
Expected units/hr81
Current units/hr78.3
Difference-3.33%
StatusOn Track
Historical rate69.7 units/hr
Based onLast 1 similar projects
Projected completion
Remaining work0 units
Current rate78.3 units/hr
Projected remaining labor0 hrs
Actual labor used12.77 hrs
Projected final labor12.8 hrs