CCProduction & Labor
MA
← All projects

Order #100129

Billing SentNormal priority

Kirra Outdoors · Gift With Purchase run · PRJ-2049 · due Aug 4, 2026

100%

500 / 500 units · 0 remaining

Open labor trackerBilling sent Aug 5, 2026

Production progress

Completed

500

Required

500

Remaining

0

Complete

100%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Kitting5005000Per Unit @ $0.506269.7On Track
Inspection5005000Per Unit @ $0.2810089.3Watch

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate12.1 hrs
Manager estimate13.4 hrs
Actual labor12.77 hrs
Projected final12.8 hrs
Variance-0.6 hrs

Productivity

Expected units/hr81
Current units/hr78.3
Difference-3.33%
StatusOn Track
Historical rate69.7 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work0 units
Current rate78.3 units/hr
Projected remaining labor0 hrs
Actual labor used12.77 hrs
Projected final labor12.8 hrs