CCProduction & Labor
MA
← All projects

Order #100134

Billing SentNormal priority

Kirra Outdoors · Seasonal Hamper run · PRJ-2054 · due Aug 19, 2026

100%

1,200 / 1,200 units · 0 remaining

Open labor trackerBilling sent Aug 20, 2026

Production progress

Completed

1,200

Required

1,200

Remaining

0

Complete

100%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Assembly1,2001,2000Per Unit @ $0.754034.3Watch
Picking / Prep1,2001,2000Per Unit @ $0.15150166.2On Track

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate40.1 hrs
Manager estimate44.3 hrs
Actual labor42.18 hrs
Projected final42.2 hrs
Variance-2.1 hrs

Productivity

Expected units/hr95
Current units/hr56.9
Difference-40.11%
StatusAt Risk
Historical rate34.3 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work0 units
Current rate56.9 units/hr
Projected remaining labor0 hrs
Actual labor used42.18 hrs
Projected final labor42.2 hrs