CCProduction & Labor
MA
← All projects

Order #100137

Billing SentNormal priority

Northline Foods · Bundle Pack 2x run · PRJ-2057 · due Aug 28, 2026

100%

600 / 600 units · 0 remaining

Open labor trackerBilling sent Aug 29, 2026

Production progress

Completed

600

Required

600

Remaining

0

Complete

100%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Kitting6006000Per Unit @ $0.506256.5On Track
Picking / Prep6006000Per Unit @ $0.15150150.8On Track

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate13.9 hrs
Manager estimate15.3 hrs
Actual labor14.6 hrs
Projected final14.6 hrs
Variance-0.7 hrs

Productivity

Expected units/hr106
Current units/hr82.2
Difference-22.45%
StatusWatch
Historical rate56.5 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work0 units
Current rate82.2 units/hr
Projected remaining labor0 hrs
Actual labor used14.6 hrs
Projected final labor14.6 hrs