← All projects
Order #100138
Billing SentNormal priorityVertex Health · Insert Card Set run · PRJ-2058 · due Aug 31, 2026
100%
750 / 750 units · 0 remaining
Open labor trackerBilling sent Sep 1, 2026
Production progress
Completed
750
Required
750
Remaining
0
Complete
100%
Services
| Service | Required | Completed | Remaining | Billing | Expected /hr | Actual /hr | Status |
|---|---|---|---|---|---|---|---|
| Assembly | 750 | 750 | 0 | Per Unit @ $0.75 | 40 | 36.8 | On Track |
| Inspection | 750 | 750 | 0 | Per Unit @ $0.28 | 100 | 115.7 | On Track |
Active employees
No employees clocked in on this project.
Labor summary
Historical estimate25.5 hrs
Manager estimate28.2 hrs
Actual labor26.86 hrs
Projected final26.9 hrs
Variance-1.3 hrs
Productivity
Expected units/hr70
Current units/hr55.8
Difference-20.29%
StatusWatch
Historical rate36.8 units/hr
Based onLast 1 similar projects
Projected completion
Remaining work0 units
Current rate55.8 units/hr
Projected remaining labor0 hrs
Actual labor used26.86 hrs
Projected final labor26.9 hrs