CCProduction & Labor
MA
← All projects

Order #100140

Billing SentNormal priority

Solace Beverages · Travel Kit run · PRJ-2060 · due Sep 6, 2026

100%

1,000 / 1,000 units · 0 remaining

Open labor trackerBilling sent Sep 7, 2026

Production progress

Completed

1,000

Required

1,000

Remaining

0

Complete

100%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Polybagging1,0001,0000Per Unit @ $0.22120123.3On Track
Picking / Prep1,0001,0000Per Unit @ $0.15150136.4On Track

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate14.7 hrs
Manager estimate16.2 hrs
Actual labor15.44 hrs
Projected final15.4 hrs
Variance-0.8 hrs

Productivity

Expected units/hr135
Current units/hr129.5
Difference-4.07%
StatusOn Track
Historical rate123.3 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work0 units
Current rate129.5 units/hr
Projected remaining labor0 hrs
Actual labor used15.44 hrs
Projected final labor15.4 hrs