Billing SentNormal priorityVertex Health · Refill Cartridge run · PRJ-2063 · due Sep 15, 2026
100%
500 / 500 units · 0 remaining
Open labor trackerBilling sent Sep 16, 2026
Production progress
Completed
500
Required
500
Remaining
0
Complete
100%
Services
| Service | Required | Completed | Remaining | Billing | Expected /hr | Actual /hr | Status |
|---|---|---|---|---|---|---|---|
| Heat Shrink | 500 | 500 | 0 | Per Unit @ $0.35 | 85 | 89.9 | On Track |
| Picking / Prep | 500 | 500 | 0 | Per Unit @ $0.15 | 150 | 161.8 | On Track |
Active employees
No employees clocked in on this project.
Labor summary
Historical estimate8.2 hrs
Manager estimate9.1 hrs
Actual labor8.65 hrs
Projected final8.7 hrs
Variance-0.4 hrs
Productivity
Expected units/hr117.5
Current units/hr115.6
Difference-1.62%
StatusOn Track
Historical rate89.9 units/hr
Based onLast 1 similar projects
Projected completion
Remaining work0 units
Current rate115.6 units/hr
Projected remaining labor0 hrs
Actual labor used8.65 hrs