CCProduction & Labor
MA
← All projects

Order #100145

In ProgressHigh priority

ABC Brands · Retail Starter Kit production · PRJ-2065 · due Oct 1, 2026

65%

325 / 500 units · 175 remaining

Open labor tracker

Production progress

Completed

325

Required

500

Remaining

175

Complete

65%

Services

ServiceRequiredCompletedRemainingBillingExpected /hrActual /hrStatus
Kitting500325175Per Unit @ $0.506252.1Watch
Picking / Prep500325175Per Unit @ $0.15150126Watch

Active employees

No employees clocked in on this project.

Labor summary

Historical estimate11.4 hrs
Manager estimate12.3 hrs
Actual labor8.82 hrs
Projected final13.5 hrs
Variance+1.2 hrs

Productivity

Expected units/hr106
Current units/hr73.7
Difference-30.47%
StatusAt Risk
Historical rate60.4 units/hr
Based onLast 1 similar projects

Projected completion

Remaining work350 units
Current rate73.7 units/hr
Projected remaining labor4.7 hrs
Actual labor used8.82 hrs
Projected final labor13.5 hrs