Order #100147
In ProgressNormal priorityVertex Health · Display Carton production · PRJ-2067 · due Oct 4, 2026
80%
800 / 1,000 units · 200 remaining
Production progress
Completed
800
Required
1,000
Remaining
200
Complete
80%
Services
| Service | Required | Completed | Remaining | Billing | Expected /hr | Actual /hr | Status |
|---|---|---|---|---|---|---|---|
| Heat Shrink | 1,000 | 800 | 200 | Per Unit @ $0.35 | 85 | 89.2 | On Track |
| Rework | 1,000 | 800 | 200 | Per Unit @ $0.65 | 55 | 57.8 | On Track |
Active employees
No employees clocked in on this project.
Labor summary
Historical estimate29.9 hrs
Manager estimate32.3 hrs
Actual labor22.82 hrs
Projected final28.5 hrs
Variance-3.8 hrs
Productivity
Expected units/hr70
Current units/hr70.1
Difference+0.14%
StatusOn Track
Historical rateNo history
Based on—
Projected completion
Remaining work400 units
Current rate70.1 units/hr
Projected remaining labor5.7 hrs
Actual labor used22.82 hrs
Projected final labor28.5 hrs