← All projects
Order #100149
PausedNormal prioritySolace Beverages · Trial Pack 3x production · PRJ-2069 · due Oct 10, 2026
50%
450 / 900 units · 450 remaining
Production progress
Completed
450
Required
900
Remaining
450
Complete
50%
Services
| Service | Required | Completed | Remaining | Billing | Expected /hr | Actual /hr | Status |
|---|---|---|---|---|---|---|---|
| Labeling | 900 | 450 | 450 | Per Unit @ $0.18 | 180 | 158.5 | Watch |
| Packaging | 900 | 450 | 450 | Per Unit @ $0.30 | 95 | 83.6 | Watch |
Active employees
No employees clocked in on this project.
Labor summary
Historical estimate14.5 hrs
Manager estimate15.6 hrs
Actual labor8.22 hrs
Projected final16.4 hrs
Variance+0.8 hrs
Productivity
Expected units/hr137.5
Current units/hr109.5
Difference-20.36%
StatusWatch
Historical rate195.3 units/hr
Based onLast 2 similar projects
Projected completion
Remaining work900 units
Current rate109.5 units/hr
Projected remaining labor8.2 hrs
Actual labor used8.22 hrs
Projected final labor16.4 hrs